Electrical infrastructure upgrade in the Comcast Denver Corporate Office.
Among the challenges of the Comcast upgrade were a condensed timeline, congested work areas, and the assurance there would be no customer cable service disruptions. The scope of work included:
- Addition of 5-sections to EM switchgear panels
- Replacement of 3-sections of main utility switchgear panels
- Installation of a 4000 AMP backup power system
- Electrical updates for multiple cooling and condenser units
During the utility power transfer, we had 24 crew members working three different shifts around-the-clock. Together, the team worked approximately 5,000 hours in seven days, to complete the power transfer.
Location: | Denver, CO |
Owner: | Comcast |
Type: | Commercial |