Electrical infrastructure upgrade in the Comcast Denver Corporate Office.

Among the challenges of the Comcast upgrade were a condensed timeline, congested work areas, and the assurance there would be no customer cable service disruptions. The scope of work included:

  • Addition of 5-sections to EM switchgear panels
  • Replacement of 3-sections of main utility switchgear panels
  • Installation of a 4000 AMP backup power system
  • Electrical updates for multiple cooling and condenser units

During the utility power transfer, we had 24 crew members working three different shifts around-the-clock. Together, the team worked approximately 5,000 hours in seven days, to complete the power transfer.

Location: Denver, CO
Owner: Comcast
Type: Commercial

Recent Projects

  • Converse County

  • 5555 Central

  • Genesis Alkali Expansion: A Testament to Dedication

  • Umoja Biopharma