30,850 Square foot 3 Phases. Occupied facility, with loss of power a critical concern. Demolition of existing footprint and new build of Multiple QRA labs, offices and conference space. New 4000 amp service with a 350 KW diesel generator backup combined with 80KVA ups system for redundant back up. 15 week schedule from start to finish.
GC: | Golden Triangle Construction Inc. |
Owner: | Micron Technologies Inc. |
Type: | Tenant Finish |